Radiant Heat Floor Design & Installation Mistakes to AvoidRadiant heating system design or installation mistakes that must be avoided.
This article explains how to avoid some fatal mistakes when installing radiant heat in a concrete floor slab by describing an incompetent radiant heat floor installation along with an explanation of why things went wrong and how to avoid these errors.
The workers in the photograph at page top, where our concrete slab was being poured, were not guilty of a thing.
But the contractor who prepared the forms and under-slab insulation placed radiant heat floor tubing too deep in the slab and he omitted proper under-slab insulation. N
The result: the owners ultimately had to abandon the entire radiant heated floor system.
InspectAPedia tolerates no conflicts of interest. We have no relationship with advertisers, products, or services discussed at this website.
- Daniel Friedman, Publisher/Editor/Author - See WHO ARE WE?
Our contractor (Nightmare-works Construction), didn't want to insulate below the radiant-heat floor slab at all, insisting that "Once you get that dirt heated up below your floor your the earth will stay warm and your home will cost almost nothing to heat."
He was dead wrong - a SNAFU that led to complete abandonment of the heating system he installed.
In the floor installation shown here, the contractor placed the radiant tubing at the very bottom of the slab; additional mistakes included incomplete or missing insulation (see the dirt in our photo just above) and radiant tubing that was in some areas buried under more than 18 inches of concrete!
The result? The building could not be heated above 60°F and in very cold weather not above about 45°F. The radiant heat floor system shown in these photographs had to be abandoned.
How to avoid some really bad mistakes when installing radiant heat in a concrete floor slab. How our contractor ruined the installation our radiant slab heating system, causing its abandonment.
How to place radiant heat tubing at the proper depth in a concrete slab. Building floor slab insulation design advice.
The nonsensical view that one can heat up the soil below an building slab on grade and that the soil would magically stay warm forever was put to the test experts when the author was five years old and the contractor was not even a gleam in his daddy's eye.
During February and March 1948, using a specially built, instrumented structure, Harlan Bareither and other experts and students at the University of Illinois Department of Mechanical Engineering conducted careful tests of various slab on grade floor and insulation designs to map heat loss, temperature, and moisture permeation characteristics of nine types of concrete slab subfloor constructions laid on the ground. [4]
Previously, the US National Bureau of Standards had already indicated that the heat loss of a concrete slab (floor) on grade (on the ground) is proportional to the perimeter of the building.
Bareither et als. referred to that work, but because the original testing was in warmer conditions (outside temperature had not been below 35°F. for more than three successive days), they recognized the need to test slab-on-grade floors in still colder conditions - in a climate where the ground is frozen during much of the heating season.
The 1948 heat loss research was important in part because it recognized that the rate of heat transfer from the heated building to the outside (earth and surrounding air) would be greater in proportion to the temperature difference between the heated space and the surrounding soils.
Photo: the radiant heat system that we had to abandon because of improper radiant heat tubing placement (too deep) and improper insulation below the slab (incomplete) includes the Thermolec B10-U electric boiler capable of providing 34,120 BTUH, circulator pumps, expansion tank, and radiant heat controls shown here as well as the entire tubing system.
One exception to the general order of priorities of where to insulate in buildings concerns homes built with slab-on-grade construction, particularly homes which have used radiant heat in the floor slab.
See details at HEAT LOSS PREVENTION PRIORITIES
The contractor (Nightmare-Works Construction) for a small cabin in the North combined being opinionated and a bully with dismal ignorance of how to construct a properly insulated radiant floor slab. [You know who you are, SB. We hope you'll read this and reconsider your opinions about radiant heat installation.]
See details at SLAB LOG CABIN SIDING - cabin photos and other comments
Not only did the owners have to battle with the bully to put insulation under the entire slab (he thought that Mother Earth would be warming the home from "ground heat" (which is below 40 °F in winter there).
Owners also lost a battle to have the contractor install proper insulation around the slab perimeter with a frost wall before the floor was poured (he insisted on a floating slab with no inside-perimeter insulation plan).
Worst of all, the contractor also pushed the radiant heat tubing so deep into the concrete (ranging from 7" deep to more than 18" deep) that the entire radiant heat system was not usable at all. Running the radiant heat pushed heat faster into the ground than it did up into the building, even with foam insulation under the slab.
We had to abandon the (expensive) radiant floor system and install alternate heating.
Details about this radiant floor slab heat failure and and research on its cause are provided below.
Also see SLAB INSULATION, RADIANT / PASSIVE SOLAR for a discussion of proper insulation below a heated floor slab.
Don't permit your contractor
to make the (many) mistakes this one did. Insist that radiant heating in a poured concrete slab have these attributes:
Radiant heat tubing in a concrete slab needs to be closer to the top of the slab than its bottom, normally in the top 2-inches of concrete.
Placing tubing deeper in the slab means, simply-put, that more heat will transfer into the slab and ultimately into the soil below than will be transferred up to the top of the slab and into the occupied space.
Our photos above and below show that the radiant heat system tubing for this improperly-installed system was placed right on top of the Styrofoam insulation intended to be at the bottom of the concrete floor slab.
This placed the tubing at varying depths but generally about 7-inches below the finished floor surface, with tubing at some locations near the slab perimeter placed 18-inches deep in the slab!
In fact the tubing was stapled directly to the surface of the Styrofoam insulation.
Re-bar was laid atop the tubing and also at the bottom of the slab. (It should have been roughly mid-slab). Placing concrete atop radiant floor PEX tubing stapled to the foam-board insulation might work IF
That was not the case for the home shown here.
After reviewing photographs taken during installation of the radiant heat floor slab described above, here's what we wrote to the owner and to the contractor:
I am doubtful that we can successfully and economically heat the cabin with radiant in floor heating as the current system is designed and installed, and it is unfortunately the case that the cost-to-cure is prohibitive as the slab would need to be completely replaced with one using proper insulation and tubing placement.
The bully contractor, who originally estimated the monthly heating cost for this small and otherwise well-insulated building, had
said the owners would face winter heating bills of about $30./month based on his prior experience.
Stunning heating bills arrived, exceeding
$400./month or more than ten times the estimated amount. That's when we began digging into the installation details of this project. Literally.
The floor slab and radiant heat tubing had been placed by the contractor while we were unable to attend the jobsite.
When the heating bills were excessive and when the heat, running 24-hours a day for weeks, was unable to raise the interior temperatures above 60°F, the contractor offered to "correct" the problem by installing larger capacity circulator pumps.
The most economical fall back is to install electric baseboard heating or possibly hydronic heating using the existing electric boiler which was installed to pump heated water through the radiant tubing in the concrete floor.
Meanwhile we shut down this unfortunate radiant slab heat system, installed a few portable electric heaters, and given the tight, well-insulated construction, we found we can keep the little cabin comfortable for a fraction of the cost of heating the earth underneath our floor with the contractor's heating installation.

In 2020, observing water leaking up through the slab in this location from below, the floor was opened to permit further investigation. Our photo above shows accumulating groundwater just below the slab insulation. A system to drain off water and prevent water entry of frost damage to the slab was needed.
Our photos above and below were made possible by breaking into the floor slab with a jackhammer, removing concrete to expose the exact details of how and where the radiant heat tubing was installed in this floor - shown below.
Following this exposure of the tubing and convinced that the radiant heat system could never work properly we removed the boiler intended for use in providing radiant heat and filled in the damaged areas of the floor with new concrete and tile.
Photographs of the slab and radiant tubing installation for the cabin show that the guidelines for radiant heat slab installations were not followed.
Repairs to this cracked ceramic tile floor are illustrated
James Darling, General Manager of Preferred Heating LLC, in Eagle River, WI commented on this article that the contractor's promise of heating the building for $20. a month was an unreasonable promise not to be relied on - one that could make the article above misleading.
We agreed that the description of the failure of this installation needed some clarification,and added the following information that should be considered:
Keep in mind that this was a small new structure (624 sq.ft.) whose construction details, methods, materials were unusually well documented as a project. So the insulation, air tightness, materials, heating details were known.
The building was super insulated, tiny, airtight, with double-glazing throughout, leading to an expected low heating cost.
If the owner's actual heating bills for the structure had been even five times what was promised for this building that was occupied only part-time, the owners would have been happy. Heating bills weren't the arm-waving promise of $20 per month, they were not $200. per month. They were more.
In fact, the utility cost to heat this tiny cabin resulted in bills that more than doubled the corresponding costs of the nearby 1960's vintage two story large old, comparatively poorly-insulated house on the same property, exposed to the same conditions.
And the exploding heating costs were observed when heating the building well before the coldest part of the heating season.
The effects of putting the tubing deep into the slab created a problem of heat transfer losses to the ground, not just a matter of longer response time to warm the building. Even if money had been no object, the system simply could not heat the building to an acceptable temperature.
The problem with very deep radiant-heat tubing, combined with incomplete insulation, is that even with just 12 to 18" of concrete above the tubing, heat flowed enough into the ground below the building that
even with the thermostat set to maximum, and running heat continuously for a week solid, in moderately cold weather (in the 40's in Northern Minnesota where in winter it can drop to 20 deg F below zero)
we never ever could get the indoor temperature above 59 to 60 °F. And this was in a new, small, airtight one-story well-insulated building.
even if we had continuous solid foam insulation under the slab, say R-10 for simplicity, if we have enough inches of concrete above, even though the "R" of concrete is much lower than the insulation, it's the total heat resistance by the total inches that comes into play.
If we have enough thickness of concrete above the tubing (Where 1" to 2" tubing depth is the best design and 6" is considered a lot, in this building we are looking at 18" or more at least in many areas, maybe 24").
With radiant tubing at those depths, the concrete begins to offer not just a lag time in heating (Mr. Darling's point) but also an actual resistance to heat transfer until we begin losing at least some heat into the ground.
The contractor and others tried to improve the system's performance by changing the boiler settings from those set by the manufacturer on its integrated circuit control board, upping the circulator size and capacity, checking flow rate through the system, checking the thermostat controls.
Our photo shows where we found the radiant heat floor tubing when we later broke open a section of the floor slab.
Radiant tubing was at the bottom of the slab, in this area more than seven inches down in the concrete, and set atop the foam sub-slab insulation.
Our PHOTO above on this page [Image file] shows that tubing was in some sections more than 18" deep, and adjacent to a large area where sub-slab insulation was simply omitted by the contractor.
We also measured floor temperatures in different areas of the building, mapping clearly where the radiant heat tubing dropped to the bottom of the footing-portion of the monolithic-slab footings!
That deep run, probably combined with the incomplete insulation at the level drop between slab bottom and the integrated footings, were almost certainly the prime cause of the failure of this system to heat the building.
As our reference document(s) below show by calculation and model, ultimately, the heat flow into the ground for tubing really too deep in the slab can be significant, even if there is insulation below all or part of the slab.
In the structure described here, not only was some tubing 12 to 18" or even more below the slab top, the insulation below the slab was incomplete, inviting ready heat flow into surrounding soils.
Despite varying opinion by some radiant floor installers, consumers, and installers as well should be wary of ignoring the advice of the radiant heating design experts and heat transfer engineers about tubing depth in radiant floor slabs shown just below.
Worse than too-deep radiant floor heating tubing, in this case, because the contractor put NO insulation at the area of soil where he stepped the slab down to the depth of the monolithic integrated footings, we have heat transfer from some of the tubing through concrete right into the cold soil, not just through concrete up into the room through the ceramic tile floor.
In this egregious error, even worse than putting radiant heat tubing too deep in the slab, insulation was simply omitted where the floating-slab monolithic footings were poured.
The R-value of concrete is roughly .08/inch (US DOE).
The builder located sections of the radiant tubing so that there was about 6" or less of concrete (in the 12" footing section") between the tubing and the cold soil, giving us a heat transmission path (tubing to soil) of R 0.24 or less.
This is a likely area of heat loss at all four sides of the building: where the slab dropped down to form footings.
See INSULATION R-VALUES & PROPERTIES
As an aside the ceramic tile on the finished floor slab was set in mastic - leaving some air spaces and mastic that is a poor conductor compared with tile set in concrete (optimal) - but we doubt that's nearly as important in the system failure in this case.
which is mistaken. In Minnesota weather sometimes reaching minus 20°F the earth forms an infinite heat sink.
Our photo (left) illustrates a successful radiant heat system installation in Minneapolis, MN - a climate similar to that where we had trouble with the Two Harbors system above.
THIS IS NOT OUR SLAB- which is has tubing at 6" deep and along one side where the tubing is deeper, 10-12" or more. We have better insulation but much deeper placement.
Here is a quote from the last page of the article which reports an expert's study of the heat characteristics that change as tubing moves lower than 3/4" from the top of the slab:
QUOTING except for [bracketed comments]
"These results indicate that tube depth does have a nontrivial effect on the thermal performance of a heated floor slab. There is a performance penalty associated with leaving the tubing at the bottom of the slab vs. positioning it near mid-depth of the slab.
The analysis performed was also based on steady state conditions. It doesn't predict the consequences of the longer response times associated with deeper tubing. These could be significant in situations where a building is recovering from a setback condition, or when heat flow from the slab needs to be reduced quickly to accommodate internal heat gains.
Considering the tradeoffs, perhaps it is time we pay more attention to quality control procedures to ensure that performance is not compromised as concrete is poured over radiant tubing circuits.
When future archaeologists dig up the ruins of our buildings several centuries from now, will they ponder why we put the heating tubing at the bottom of the slab? Might they wonder if we didn't know any better?
Would they conclude that some builders of the time were just too lazy to bother lifting the tubing? Thinking back to how ancient Romans used lead piping for water supplies, perhaps those archaeologists will conclude that even after centuries of experience, we still had a hard time doing this pipe thing right.
[FIGURE 4 OMITTED], [FIGURE 5 OMITTED]
| Table of Insulation Material Properties | ||
| Average water temperatures needed for heat output of 15 and 30 Btuh/sq ft. | ||
| Upward Heat Flux Requirement (Btuh/[ft.sup.2]) | Tubing Depth 2" Below Slab Surface, Average Water Temp. Required °F. | Tubing Depth at Bottom of 4" Slab, Average Water Temp. Required °F. |
| 15 Btuh | 95 °F | 102 °F |
| 30 Btuh | 120 °F | 134 °F (1) |
(1) regarding the "134 °F" in the bottom right of the above table:
This is moving down just 2" deeper. We estimate maybe 168 degrees water temperature would be needed at 4" down and
well over 200 deg heating water would be needed in tubing 6" down.
In the slab in our construction project, the critical
tubing, leaving the heating boiler, was placed more than 12" deep in poured concrete.
Heating energy costs will increase consistent with the increase in heating water operating temperature requirements.
Below see our list of RADIANT HEAT DESIGN & INSTALLATION MANUALS
Reader Question from Wenell: I would like to know what the persons that wrote and researched this article thinks about what Montana has on research.
On their web page MONTANA SLAB EDGE INSULATION ANALYSIS FOR 2006 IECC ADOPTION [PDF] There seem to be so many theories on this.
One thing we have found that if the soil conditions are quite damp, there definitely needs to have some type of insulation under the slab.
Another theory I have read is that the heat as it goes down, which it will, some is that it radiates horizontally, which makes insulating the edge quite well. - Wendell Schubloom
Wendell, there is not actually any contradiction between the Montana (DOE) research you cite above and radiant heat floor slab insulation requirements.
The study you cite does not focus on radiant slab heating designs but or a more narrow question about the benefits of foundation/floor slab perimeter insulation.
The DOE photo (below left) shows a typical Montana construction practice that gives a thermal break between a concrete floor slab (not yet poured) and the exterior foundation wall.
I've read quite a lot of supporting research on slab and slab perimeter insulation for radiant heat flooring, and I have some direct experience with installing radiant heat and more with inspecting radiant heat flooring problems.
Quoting from the conclusions of the Montana DOE-sponsored study you cite, [2] [photo at left showing interior foundation insulation before the slab is poured, U.S. DOE, op cit.]
This study shows that insulating slab edges with R-10 insulation to 4-ft depth along the slab edge saves about 3% annual energy and reduces annual fuel cost by between 1 and 2%. The energy savings vary slightly depending on the insulation configuration and building type.
Although the current installation practice in Montana does not extend the interior footing insulation to the top of the slab, based on empirical data, this study concludes that irrespective of the insulation installation configuration, Montana buildings will save energy by insulating the slab edge with R-10 insulation to a depth of 4 ft.
The payback period could vary from 4 years for small retail commercial buildings to 12 years in small office buildings.
This study, using eQUEST, Version 3.0 simulation modeling, compared full versus partial slab perimeter insulation schemes and found that there was useful energy cost savings even with partial insulation.
The study data includes comparison with fully-insulated slabs too, but most important for our discussion, it does not address radiant-in-floor-slab heating designs that, without full insulation, can find an easier heat flow into the ground than into the building - not what we want to see nor pay for in heating bills. Quoting:
The local practice of insulating the slab footing on the interior allows heat loss along the slab perimeter and thus does not achieve the full savings that could be achieved with full edge insulation configurations, but the savings are still significant.
The risk in misinterpreting the Montana study conclusions above would be to apply them generally to radiant heat floor designs and that to improperly infer that complete under-radiant-heat-floor-slab insulation is not needed in cold climates.
That study makes a general conclusion for all Montana buildings and by no means does the conclusion adequately address radiant in-slab heating system designs.
The fallacious concept held by the contractor in our horror story was that "once you heat up the earth below your building it will start "giving back" heat to the building and you'll be just fine. His theory was nonsense, as both expert advice and actual field experience proved.
The earth in a cold climate like Montana or Minnesota, is for practical and design purposes, an infinite heat sink. A radiant floor slab heating system will, if improperly designed, keep pumping heat into the ground as long as the heat is turned on.
Forever.
We saw this in astronomical heating bills and a cold building interior in the Minnesota home discussed above. Heat always flows, and continues to flow from a warmer material into a cooler material.
Heated the soil beneath a building where insulation was incomplete, inadequate, or omitted, will never reach some magic perimeter after which it stops sending heat into the surrounding soil any more than an ice cube placed into the sea will stop melting because it's "cooled down" the water around itself.
As the principal author of this material I relied largely on the concrete industry and the radiant flooring industry's radiant floor slab design specifications and advice [1] as they, above all, have a huge vested interest in their installations being successful.
There is no doubt that in virtually every radiant-heat-floor-slab design we need continuous insulation under the slab and at slab perimeter, though the appropriate insulation amount might vary depending on the local climate.
The folks who seem to disagree have been people like the bully contractor who himself admitted he had never read instructions, attended a class, nor asked for expert advice.
As is often the case with small contractors in remote areas and without expertise, he was "winging it". Don't try mentioning "thermodynamics" or "heat flow theory" to a bully.
Just how bad an uninsulated, under-insulated, or incompletely insulated floor slab will perform with radiant in-slab floor heating depends on some additional variables: climate, soil moisture (read thermal conductivity as you suggest), and critically, the depth of tubing in the slab. In ALL cases we want the insulation in place.
But in the horrible installation we describe in these articles, the contractor not only provided incomplete and no perimeter slab insulation, he also buried the tubing so deep in the concrete that heat moved much more down into the cold earth than upwards into the occupied space.
There was so much heat loss that we could not get the room temperature up even in cold but not bitter cold weather, and even though the same contractor had done a great job insulating the upper portions of the structure's roof and walls. (He was a framer/carpenter, and should not have attempted radiant slab installation nor tile work.) That's why we had to abandon the whole radiant floor installation.
If the floor slab had been very well insulated, the installation still would not have performed well because of the excessive tubing depth in the slab ( over 12" down in some sections ).
I appreciate the Montana reference and have added it to this article below at references [2].
We are in the steel building business so we have a lot of in floor heat done. with the experienced heating people we use, have had no problems.
But the question I have is- in North and South Dakota there is a Cat dealer by the name of ButlerCat.
They have built huge shops and I found out this spring what they do for floor hear.
They place the foam down and put the PEX directly to this and then place 4 to 6" of sand on top before pouring the floor. I ask why and was told if the have any floor problems they can remove any thing need to. They done this on I think four bldg's
What are your thought's
Wendell it's a fair question, and I welcome the discussion. But I suspect this may be a case of intelligent people who think things up on their own, make up an explanation that sounds reasonable, but may not know the whole story.
The deeper you put radiant heating tubing in the slab the worse the heating system will perform in delivering heat to the interior. Furthermore, the thermal conductivity of sand is much below that of tubing directly in contact with the concrete slab itself.
The expert sources I found on this want tubing in the concrete and very close to the slab top surface, an inch or two at most down is best.
I agree that if there is enough insulation under the slab and it's well done and complete, in the design (foam, tubing, sand, concrete) you describe you will eventually probably warm the slab upper surface, but consider that there are heat flow rates through insulation too, it's not "heat proof".
With 6" of sand and say nominally 6" of concrete, your tubing is 12" down - way too deep, and furthermore, the first 6" of material (sand) between the tubing and the occupied space, does not quite the same level of thermal conductivity as tubing in contact with solid concrete.
The sources I cite at references below point out that there is heat flow resistance through concrete and sand as well.
So while it may not be intuitively obvious, and while it's true that the thermal conductivity of concrete and even sand (which is not as good as concrete) is greater than insulation, if we have enough sand or concrete above the tubing, and little-enough insulation below the tubing, heat flow down through the insulation can still be significant.
Think of it as "heat flow resistance" through various materials. You can have a more conductive material above the tubing, but if you have a lot of it, the total heat flow resistance can still be significant.
Finally, the supposition that "if they have floor problems they can remove anything they need to" sounds highly suspect to me - it's not thought out. In any case you'd have to chop entirely through the floor slab to get to the tubing below, and meanwhile you are paying in higher heating bills than necessary over the life of the building.
The following unedited discussions, a continuation of RADIANT HEAT MISTAKES, illustrates efforts to track down the reason that a radiant-heat slab system is not heating adequately.
Also see RADIANT HEAT DESIGN FAQs - questions & answers about installing & troubleshooting radiant heating systems
In the case study starting at RADIANT HEAT MISTAKES some portions of the slab or insulated but the installer left whole sections just exposed to the dirt. We would never have found which sections of insulation were omitted if we haven't had the photos. Similarly his second and fatal radiant heat installation mistake was putting the tubing at the bottom of the slab.
We couldn't see those details without destructive chopping up of the concrete or finding photos taken during construction.
My point is that drilling one inspection hole in a radiant heated floor to examine the insulation scheme and tubing depth, even if you could avoid cutting tubing, wouldn't assure you that there wasn't a problem elsewhere under the floor.
For a really bad radiant installation with tubing too deep (common) or incomplete insulation (somewhat common) I abandon the system - painful as that is, as it makes no sense to just pump heat and dollars into the ground all winter.
For a case that can't be fixed above the slab (like air leaks) I'd install an alternative that's least disruptive, such as wall mounted split-system heat pump.
Now moved to RADIANT HEAT DESIGN & INSTALLATION MANUALS
Thank you for your time, Dan. Sites like this can help a *lot* - we were educated enough to understand what was going on, ask reasonable questions and help with the debugging process, and had a contractor who would work *with* us. As a partnership we got this resolved better and faster. - On 2015-01-03 by Susan -
I really appreciate this site. Lots of great info here. - On 2018-05-22 by Tim
...
Continue reading at RADIANT HEAT TEMPERATURES or select a topic from the closely-related articles below, or see the complete ARTICLE INDEX.
Or see RADIANT HEAT MISTAKES FAQs - questions, comments, arguments posted originally at this page.
Or see these
RADIANT HEAT MISTAKES at InspectApedia.com - online encyclopedia of building & environmental inspection, testing, diagnosis, repair, & problem prevention advice.
Or see this
Or use the SEARCH BOX found below to Ask a Question or Search InspectApedia
Try the search box just below, or if you prefer, post a question or comment in the Comments box below and we will respond promptly.
Search the InspectApedia website
Note: appearance of your Comment below may be delayed: if your comment contains an image, photograph, web link, or text that looks to the software as if it might be a web link, your posting will appear after it has been approved by a moderator. Apologies for the delay.
Only one image can be added per comment but you can post as many comments, and therefore images, as you like.
You will not receive a notification when a response to your question has been posted.
Please bookmark this page to make it easy for you to check back for our response.
IF above you see "Comment Form is loading comments..." then COMMENT BOX - countable.ca / bawkbox.com IS NOT WORKING.
In any case you are welcome to send an email directly to us at InspectApedia.com at editor@inspectApedia.com
We'll reply to you directly. Please help us help you by noting, in your email, the URL of the InspectApedia page where you wanted to comment.
In addition to any citations in the article above, a full list is available on request.