Mound septic system designs.
Mound Septic System design, install, maintain, repair: this document discusses the use of septic mound systems as an alternative septic system design. A septic mound is an engineered system involving fill to create a soil absorption system for the disposal of septic effluent.
Septic mound systems are used where local soils are not suitable for effluent disposal. In the sketch shown here, effluent is discharged to the septic mound by a pumping chamber. (Source: US EPA) Alternatively a septic mound, if suitably located, may be supplied effluent by gravity feed.
InspectAPedia tolerates no conflicts of interest. We have no relationship with advertisers, products, or services discussed at this website.
- Daniel Friedman, Publisher/Editor/Author - See WHO ARE WE?
Mound Septic Systems are a wastewater absorption trench system which has been constructed using "suitable soil-fill material" which has been placed on top of the natural soil on a building lot. Mound systems are often confused with "raised septic bed systems" but have different design requirements, are generally smaller in total size, and depend on the fill material for successful wastewater treatment.
Raised bed septic systems are constructed in fill over soil which can accept septic effluent below the fill. Mound septic systems are constructed in fill over soil which does not acceptably treat septic effluent below the fill - all of treatment occurs in the mound.
Other requirements differ as well, as described, for example, in the New York standard for mound systems Appendix 75-A.9 reproduced below.
Site conditions such as sandy (permeable) soil with high groundwater levels, soils with poor percolation rate, and very rocky sites preclude installation of a conventional septic leach field as they lack adequate depth of proper soil in which effluent treatment could occur.
For these conditions, additional fill is brought to the site and installed in an area and depth sufficient that all of the effluent treatment occurs in the mound.
Effluent may enter the mound by gravity if site slopes permit, or effluent may have to be pumped up into the mound from a pumping station. In this latter case the pumping station would usually be in a second septic tank which receives clarified effluent from the primary tank.
Mound systems were developed by the North Dakota Agricultural College in the 1940's [Kahn, Allen, Jones cited at "More Information" below] with further studies of effective mound designs in the 1970's.
Inspecting mound systems in New York State I have often seen improperly constructed mounds including efforts by the builder to save on fill cost by using the "mound" as a place to first pile up all of the trees and tree stumps which needed to be cleared from the site, covering this mess with a too-thin layer of fill soil in which the septic absorption trenches are installed.
The result is a mound system with a short life. If you see trees poking out from the perimeter of your mound further investigation may be in order. Also watch for effluent breakout around the bottom edges of the mound.
Improper mound siting is found at some properties where the builder fails to consider site runoff or natural groundwater paths.
One mound system was constructed using too little fill and placed over what had been a stream bed. My septic dye test very quickly produced red-dyed effluent at the low end of the mound where a seasonal stream continued to run under the mound in wet weather.
Placing a mound septic system on a steep slope, over a stream bed, over a natural drainage swale (photo of this defect), specifying an under-sized mound for the anticipated usage level, and poorly installed piping which does not slope properly or which becomes disconnected, and finally, use of improper soil which lacks the proper percolation rate all result in a costly installation with a too-short life.
Traffic: As with any septic absorption system, heavy traffic over the mound can compress soil or break pipes, rendering the system inoperative and requiring costly repairs. At a recent inspection I found that the septic mound had been placed over a roadway connecting two properties owned by the same family.
Family members continued to drive back and forth between homes right over the septic mound. Its future life was rather doubtful. Driving vehicles over the septic mound or other drainfield, even for a single project such as construction of a nearby structure or performing other site work, is likely to damage the system and lead to need for costly repairs. Kahn et als. also advise keeping grazing animals, horses, cows, etc. off of mound systems.
Structures, Paving, Patios: Covering a septic mound, such as by installation of paving, a patio, or weed-blocking solid plastic, will damage the mound and prevent proper operation by blocking both oxygen intake into the soil and also evaporation of effluent from the soil top.
Blocking or sealing the ground surface will be a problem over just about any septic effluent absorption field. Don't build anything over a septic mound, no building, no fish pond, no patio, no tennis court, no parking area, no playground (compacts the soil).
Grasses, weeds, flower are OK: Many people have written to ask me what can be planted over a septic field.
The best answer is grass or native grasses and weeds. Flowers are ok so long as they are not varieties which send down deep roots. Basically, any shallow-rooting planting will be ok over the surface of a septic mound or over most other septic drainfields.
Stay away from trees or shrubs which are likely to put down deep roots. The roots will quickly invade and clog the buried effluent lines and may also cause them to move, break, or become disconnected.
Some experts (Kahn, Allen, Jones) also point out that if you're planting on the edges and lower toe of a septic mound, those plants need to be able to tolerate the higher moisture levels found in those parts of the mound system.
Trees are not OK: Kahn, Allen, Jones (book cited below) that trees such as bamboo, willow, eucalyptus, cypress, Monterey pine, pepper, and walnut have particularly aggressive and deep roots. Keep such trees at least 100 feet from the septic field.
Ivy, Pachysandra, Similar Ground Covers are not OK: because these plants will reduce effluent evaporation from the mound soils and because their roots often invade and clog effluent distribution piping.
Details are at PLANTS & TREES OVER SEPTIC SYSTEMS - home
In New York State a septic mound over rocky soil may cost double a conventional leach field even where a pumping station is not required. (Perhaps $15,000 to $20,000). Septic mounds require a larger area than leach fields in good soil.
If a pump station is required, some additional monitoring and maintenance is required, and of course if there is no electric power to run the pump, the size of the effluent holding tank will determine how many days of system operation are available in event of a power failure.
The following detailed specification for installation of a septic mound system is from: New York Appendix 75-A.9 Alternative Septic System Designs section 9.c Mound Septic Systems
Photo above: Site work in preparation to construct a septic mound includes assuring good drainage of surface runoff away from the area where any type of septic effluent disposal system is to be constructed.
Title: Appendix 75-A.9 - Alternative Septic Systems [Regulation and System Design Criteria for Raised Septic Systems,
Septic Mound Systems, Intermittent Sand Filter Bed Systems, Evaporation-Transpiration Septic Systems,
Evaporation-Transpiration Absorption Septic Systems, and Other Alternative Septic Systems]
Effective Date: 12/01/1990
A mound septic system (or septic mound system) is a soil absorption system that is elevated above the natural soil surface in a suitable fill material. It is a variation of the raised bed utilizing sandy fill material but not requiring a stabilization period prior to the construction of the absorption area.
On sites with permeable soils of insufficient depth to groundwater or creviced or porous bedrock, the fill material in the mound provides the necessary treatment of wastewater.
The overall size of the mound system will normally be substantially smaller than a raised bed.
[DF: Note: while they are similar in design "mound septic systems" discussed here are not identical to "raised septic systems" discussed at Raised Septics which have different site requirements.]
A mound system may be used where all the following conditions are found:
(i) The maximum high groundwater level must be at least one foot below the original ground surface.
(ii) Bedrock shall be at least two feet below the natural ground surface.
(iii) The percolation rate of the naturally occurring soil shall be faster than 120 minutes/inch.
(iv) The natural ground slopes shall not exceed 12%.
(v) All minimum horizontal separation distances can be maintained as described in Table 2.
(i) The designer shall consult with the health unit having jurisdiction regarding the method for detailing the hydraulic design.
(ii) The basal area of a mound system is defined differently than a raised bed. The basal area for a system on level ground includes all the area beneath the absorption trenches or bed and the area under the tapers.
Table 1-A* Comparison of site limitations for subsurface soil absorption systems and mound systems |
||
Site Limitations on Drainfield or Soakaway Beds | Septic Mound System Specifications | Subsurface Soil Absorption System |
---|---|---|
Depth to limiting layer (inches) | At least 24" | At least 60" |
Percolation rate (min/inch) | More than 3 min/in less than 120 min/in | More than 3 min/in, less than 60 min/in |
Slope | Less than 15% grade | Less than 15% grade or slope |
|
* Table 1. is derived from Septic Tank - Mound System, AEX-744, [PDF] Karen Mancl, the Ohio State University Extgension Fact Sheet. We will add data to this table with examples of other septic mound system design specifications from other suggested sources.
CONTACT us with suggestions.
...
Table 1-B Septic Mound Effluent Disposal System Design Specifications |
||
Septic Mound Site Characteristics | Slowly-Permeable Soils | Permeable Soils |
Soil Percolation Rate 1 | 60 - 120 minutes per inch (mpi) | up to 60 mpi |
Depth to bedrock or imperable soils | 60 inches | 60 inches |
Slope or grade [original grade] | 6% or less | 12% or less |
Depth to groundwater | over 24 inches | over 24 inches |
Sources:
On a sloping site, the basal area includes only the area under the absorption trenches/bed and the lower or downhill taper. The basal area is designed upon the percolation of the naturally occurring soil. [Also see (iv) below for more steep slope design notes.]
Where the percolation rate is 60 min/in or faster, refer to TABLE 4B - SOIL APPLICATION RATES
(iii) Percolation tests for the [mound system] fill material shall be conducted at the borrow pit. Only soils with a percolation rate between five and 30 minutes per inch shall be used for the fill material. Sands with greater than 10% by weight finer than 0.05 mm material must be avoided.
At least 25% of the material by weight shall be in the range of 0.50 mm to 2.0 mm. Less than 15% of the material by weight shall be larger than a half-inch sieve. A sieve analysis may be necessary to verify this requirement. The required absorption area is based upon the percolation rate of the fill material as determined from Table 4B [link given above].
(iv) The [septic mound] system [effluent piping] shall be designed to run parallel with the contours of the site. The width of the system (up and down the slope) shall be kept to a minimum, but in no case shall the absorption area be wider than 20 feet. In a distribution network using a center pressure manifold, distribution lines shall have a maximum total length of 200 feet.
In a network septic system mound drainage bed using an end manifold, distribution lines shall have a maximum length of 100 feet.
(v) [Septic] Mound dimensions shall meet or exceed those required by the health unit having jurisdiction.
(vi) A [septic effluent] pressure distribution network shall be required.
(vii) A dual chamber septic tank or two tanks in series in addition to the dosing tank shall be provided [for network septic mound drainage bed or soakaway bed systems]
A gas baffle or other outlet modification that enhances solids retention is recommended [for septic mound pressure distribution systems]
Above: a septic mound system under construction at a property in northern Minnesota. The contractor removed trees and fallen trees but left stumps in place (this helps keep the soil stable), and was bringing in suitable fill to construct the septic mound when these photos were taken.
(i) Heavy construction equipment shall not be allowed within the basal area and area downslope of the system which will act as the dispersal area for the mound.
(ii) The vegetation shall not be scraped away, roto-tilled, or compacted.
Excess vegetation shall be removed with trees cut at the ground surface but stumps left in place.
The area shall be plowed to a depth of seven or eight inches with a double bottomed blade/furrow plow and the furrow turned upslope.
(iii) The fill material is placed from the upslope side of the system to the full depth required in the design and shall extend to the edge of the basal area at a slope not to exceed one vertical to three horizontal.
(iv) The absorption area is then formed within the mound. A minimum of six inches of aggregate shall be placed beneath the distribution lines.
(v) The pressure distribution lines are placed parallel to the contours of the slope and a minimum of two inches of aggregate is placed above the lines.
(vi) A permeable geotextile is placed over the entire absorption area to prevent the infiltration of fines into the aggregate.
(vii) On sloping sites a diversion ditch or curtain drain shall be installed uphill to prevent surface water runoff from reaching the absorption area.
Curtain drains or intercept drains can protect septic drainfields in areas of wet soils or surface and subsurface groundwater
(viii) A minimum of six inches of finer materials such as clayey loam is placed over the top of the absorption area, and the entire mound including the tapers is then covered with six inches of top soil and seeded to grass.
I built my home on low property which used to hold water. I had to have a mound system built per the local health department.
My question is now that I have this beautiful home, how can I get rid of the unsightly mound in my backyard? Are there any alternatives to the mound system? - Tim Murray
There are many design alternative to septic mound systems, such as installing other advanced wastewater treatment systems, evaporation transpiration systems, and others. But these are costly and don't make sense if you already have a properly functioning, recently installed septic mound system.
In general, a "septic mound" is a raised septic bed intended to get septic effluent processing and disposal high enough above the local water table that you are not contaminating the environment.
In most septic mound designs nothing precludes bringing in still more fill so that the "mound" is more gracefully integrated into the rest of the site by adding fill around the mound perimeter, making the "mound" into a more gently sloped terrain feature.
Watch out: if you decide to add tons more soil to beautify the site around the mound, do not under any circumstances let the equipment operators drive over the septic mound, or it will almost certainly be destroyed. Also, don't add more soil on top of the mound - you may interfere with its proper operation.
Watch out:Furthermore you need to be sure that you have not interfered with surface runoff or surface drainage that needs to be directed away from the sepic mound, and you'll want to check with the original septic design engineer to be sure that your added fill doesn't interfere with the transpiration feature of the septic mound: by filling against the sides of a septic mound you may be reducing the original mound's ability to dispose of some effluent by evaporation.
Finally, while improving the contours of your home site, be sure that you make the final site grading design one that directs surface runoff and subsurface runoff away from the septic mound area. Directing groundwater onto the septic mound will prevent it from working and shorten its life.
Above: new septic mound is straw-covered; this amount of straw will help prevent erosion of the mound until grass has been established. But it is not enough straw to protect the new mound system from freezing.
...
Below you will find questions and answers previously posted on this page at its page bottom reader comment box.
@Field Inspector K,
In my opinion, while it's not an emergency, you should clear fallen tree(s) from the septic mound for several reasons:
1. you can then inspect to be sure that no tree branch punctured and damaged one of the effluent lines - you'd want to repair that. Look for branches that speared into the soil, especially along the more-flat top of the mound area. Normally inspection ports will mark the location of each line.
2. you want to avoid further soil compression
3. you want to avoid the development of runoff channels that might over time erode the mound soil cover
but
Watch out: don't let some heavy handed bloke drive his backhoe or other heavy equipment over the mound for any reason, including tree removal, as doing so risks compressing the soil and damaging the mound.
Thanks for the helpful question and photo - we'll move this discussion to
MOUND SEPTIC SYSTEMS https://inspectapedia.com/septic/Septic_Mound_Design.php and welcome any further questions, comments, suggestions.
On 2021-07-29 by Field Inspector K
A medium-large tree fell on top of the septic mound system during a recent storm [photo above].
Should I worry about it lying there?
Would it damage the septic mound to just leave it there? It's too large for me to move by myself.
This Q&A appeared originally at TREES or SHRUBS OVER THE SEPTIC FIELD or TANK
On 2019-01-04 by (mod) - If the septic is backing up the cause may be:
If the septic is backing up the problem could be any of a number of issues such as
a failed drainfield that is clogged or saturated - not something that is ever fixed by pumping the septic tank
a blocked effluent line between tank and drainfield
damaged septic tank baffles or baffles that are missing - something that could be discovered during pumping
Ask your septic contractor to help diagnose the problem by inspecting the level of sewage in the tank, the condition of the baffles, and the occurrence of backflow of effluent into the septic tank during or after it was pumped out.
Also check the D-box effluent levels for signs of flooding.
On 2019-01-03 by yves
have a mound system .pumped out 6 months ago and told that we should have 2 yrs before next pump out but its already backing up in the house what do you think the problem is
On 2018-08-17 - by (mod) -
Anon the mound height can easily be 4 to six feet in height. Figure that the BOTTOM of the effluent trenches needs to be 24" or more above the seasonal high water table.
On 2018-08-17 by Anonymous
HOW high does a sand mountain on a septic
On 2017-08-24 - by (mod) -
Soil suitable for planting grass.
On 2017-08-24 by Bern
What type of soil would you use to topup mound
On 2017-05-23 - by (mod) -
Heather,
You may want to review the septic mound layout and site plan with your building or health department before raising an issue here. It might be that the size or area required to meet code for adequate capacity meant the mound wouldn't fit except diagonally.
On 2017-05-23 by Heather
We were shocked to find our septic mound placed diagonally across our back yard. The placement severely limits how we can use our yard. We were told that it HAS to be there. Before we were told that it was going to run along the side of the yard. Can this be true? It HAS to be in a particular spot? I thought we would have options. Our yard is ruined!
On 2016-08-09 by (mod) - Do you always need septic tanks pumped dry for septic repair work?
No, David, the requirement to pump out a septic tank completely for repair work depends on the repair needed. For example it MIGHT be possible to replace a damaged tank baffle by pumping the tank level down but not out completely.
The HAZARD is that simply leaning over a septic tank can be fatal: the worker can be overcome by methane fumes, faint, fall into the tank, and die. Those hazards are not reduced to zero even if a septic tank is pumped "dry" or "out" completely, as the gases remain.
That's why experts never work alone, wear protective equpment, and are not so stupid to do as one fellow I know who lit a cigarette while looking into the septic tank: he caused a methane gas explosion.
On 2016-08-09 by David
Do you always need tanks pumped dry for repair work?
(Mar 8, 2014) vswift said:
Very helpful information but I would like to know if there are any problems with flushing toilet paper.
V.S. - if your septic tank is working properly and its baffles are intact it will keep any toilet paper in the septic tank and out of the drainfield. In that case flushing toilet paper is OK.
However often at older buildings with smaller-diameter or clog-prone building drains you may be requested to dispose of toilet tissue in a separate waste container rather than flushing it down the drain.
For a list of things that should not be flushed down building drains
(May 4, 2014) kay said:
Do mound systems need to be pumped same as conventional systems? Thank you
Kay,
Thanks for the question. The answer is absolutely, yes. But let's be more clear. You don't pump the "mound" - the mound is a raised body of earth into which the septic tank's effluent is discharged for treatment and absorption into the soils.
What gets pumped or cleaned out periodically is the septic tank. Doing so extends the life of the septic mound by keeping the septic tank from becoming so full that it discharges solids along with the wastewater or under-treated wastewater into the mound.
See SEPTIC TANK PUMPING SCHEDULE
We just recently moved onto an acerage and over the winter we started having issues with our mound.. We had a blow out and at first the discharge was white and we called a septic guy and he gave us some active enzymes to add to out tank.. But now the discharge is black & white.. We have cut our water consumption in half (3 soon to be 4 people).. Is there anything at all be can do to fix this? - V.L. 6/16/2014
V.L.:
No enzyme, no additive, no treatment that is legal is going to fix a failed septic mound. You would be better served giving that money to a charity rather than flushing it down the toilet.
See CHEMICALS & TREATMENTS for SEPTICS.
What's needed is a more careful diagnostic to discover just what's wrong: a broken or clogged pipe, or more costly, clogged soils and a failed absorption field.
At SEPTIC FIELD FAILURE CAUSES we list causes of field failures that may help you in diagnosis.
...
Continue reading at SEPTIC MOUND DESIGN SPECIFICATIONS or select a topic from the closely-related articles below, or see the complete ARTICLE INDEX.
Or see these
MOUND SEPTIC SYSTEMS at InspectApedia.com - online encyclopedia of building & environmental inspection, testing, diagnosis, repair, & problem prevention advice.
Or see this
Or use the SEARCH BOX found below to Ask a Question or Search InspectApedia
Try the search box just below, or if you prefer, post a question or comment in the Comments box below and we will respond promptly.
Search the InspectApedia website
Note: appearance of your Comment below may be delayed: if your comment contains an image, photograph, web link, or text that looks to the software as if it might be a web link, your posting will appear after it has been approved by a moderator. Apologies for the delay.
Only one image can be added per comment but you can post as many comments, and therefore images, as you like.
You will not receive a notification when a response to your question has been posted.
Please bookmark this page to make it easy for you to check back for our response.
Our Comment Box is provided by Countable Web Productions countable.ca
In addition to any citations in the article above, a full list is available on request.