InspectAPedia ® Home ENVIRONMENTAL HAZARDS - INSPECT, TEST, REMEDY ACOUSTICAL SEALANT CHOICES AIR CONDITIONING & HEAT PUMP SYSTEMS AGE of a BUILDING - how to determine AIR BYPASS LEAKS AIR CHANGE RATE ACH HEAT SAVINGS AIR FILTERS for HVAC SYSTEMS AIR LEAK DETECTION TOOLS AIR LEAK MINIMIZATION AIR LEAK SEALING PROCEDURE AIR TEST FOR MOLD: ACCURACY AIR TEST SAMPLING CASSETTE STUDY ALLERGEN TESTS for buildings ALLERGENS in BUILDINGS, RECOGNIZING ALLERGY & MOLD IAQ PRODUCTS ALLERGY TESTS for PEOPLE ALLERGY TEST ACCURACY ANIMAL ALLERGENS / PET DANDER APPLIANCE EFFICIENCY RATINGS ASBESTOS IDENTIFICATION IN buildings ATTIC LEAKS, CONDENSATION & MOLD ATTIC VENTILATION BASEMENT CEILING VAPOR BARRIER BASEMENT HEAT LOSS BASEMENT LEAKS, INSPECT FOR BASEMENT WATERPROOFING BATH & KITCHEN DESIGN GUIDE BATHROOM VENTILATION BIOGAS PRODUCTION & USE BLOWER DOORS & AIR INFILTRATION BLOWER FAN CONTINUOUS OPERATION BLOWER FAN OPERATION & TESTING BLOWN-IN INSULATION BRICK LINED WALLS BRICK VENEER WALL AIR LEAKS BRICK VENEER WALL Loose, Bulged BRICK WALL DRAINAGE WEEP HOLES BUCKLED FOUNDATIONS due to INSULATION? BUILDING NOISE DIAGNOSIS & CURE CATHEDRAL CEILING INSULATION CATHEDRAL CEILING VENTILATION Ceramic Insulation CHIMNEY INSPECTION DIAGNOSIS & REPAIR CHINESE DRYWALL HAZARDS COOLING LOAD REDUCTION by ROOF VENTS COMBUSTION AIR for TIGHT buildings CONDENSING BOILERS/FURNACES DAMAGE CRAWL SPACES DEFINITION of Heating & Cooling Terms DIAGNOSE & FIX AIR CONDITIONER / HEAT PUMP DIAGNOSE & FIX HEATING PROBLEMS-BOILER DIAGNOSE & FIX HEATING PROBLEMS-FURNACE DIRECT VENTS / SIDE WALL VENTS DIRECTORY of OIL TANK EXPERTS DRAFT HOODS - gas fired DRAFT MEASUREMENT, CHIMNEYS & FLUES DRAFT REGULATORS, DAMPERS, BOOSTERS DUCT INSULATION - Asbestos Paper DUCT SYSTEM & DUCT DEFECTS ELECTRIC HEAT ENERGY STAR PROGRAM EVAPORATIVE COOLING SYSTEMS Fiberboard Insulation Sheathing Mold FIBERGLASS HAZARDS FIBERGLASS PARTICLE CONTAMINATION TEST Fiberglass Enviro-Scare FIBERGLASS INSULATION FIBERGLASS INSULATION MOLD FINANCIAL AID FIREPLACES & HEARTHS FLAT ROOF MOISTURE & CONDENSATION FLOOR RADIANT HEAT Mistakes to Avoid FOUNDATION WATERPROOFING FRENCH DRAINS FRAMING DETAILS for BETTER INSULATION FRAMING DETAILS for DOUBLE WALL HOUSES FRAMING METAL STUD PERFORMANCE FREEZE-PROOF A BUILDING FROST HEAVES, FOUNDATION, SLAB GEOTHERMAL HEATING SYSTEMS GREEN BUILDING CONSTRUCTION CODES GUIDES GREENHOUSE DESIGN for SOLAR HEATING GREENHOUSE / SUNSPACE GLARE HEAT LOSS in BUILDINGS HEAT LOSS DETECTION TOOLS HEAT LOSS INDICATORS HEAT LOSS PREVENTION PRIORITIES HEAT LOSS R U & K VALUE CALCULATION HEAT LOSS RATE CALCULATIONS HEAT PUMPS, DIAGNOSIS, REPAIR HEAT TAPES & CABLES on Roofs for Ice Dams HEATING COST SAVINGS METHODS HOW TO REALLY CUT HOME HEATING COSTS HEATING TUNUP PRIORITIES ENERGY SAVINGS PRIORITIES VENTILATION, BALANCED HEAT COST SAVINGS HEATING COST FUEL & BTU Cost Table HEATING LOSS DIAGNOSIS-BOILERS HEATING LOSS DIAGNOSIS-FURNACES HEATING OIL - OLD, USEABLE? HEATING OIL PIPING TROUBLES HEATING OIL SHELF LIFE HEATING OIL SLUDGE HEATING OIL USAGE RATE HEATING SMALL LOADS HEATING SYSTEMS HEATING SYSTEM INSPECTION PROCEDURE HOUSEWRAP AIR & VAPOR BARRIERS HOUSEWRAP INSTALLATION DETAILS HOUSEWRAP at SILLS, SOLES, TOP PLATES HOUSE DOCTOR, how-to be HOT ROOF DESIGNS: Un-Vented Roof Solutions HUMIDITY LEVEL TARGET ICE DAM PREVENTION INDOOR AIR QUALITY & HOUSE TIGHTNESS INDOOR AIR QUALITY IMPROVEMENT GUIDE INSULATION CHOICES Insulation Air & Heat Leaks INSULATION FACT SHEET- DOE INSULATION for GREENHOUSE or SOLARIUM INSULATION IDENTIFICATION GUIDE INSULATION INSPECTION & IMPROVEMENT INSULATION LOCATION - WHERE TO PUT IT INSULATION MOLD INSULATION R-Values & Properties KIT HOMES, Aladdin, Sears, Wards, Others KITCHEN & BATH DESIGN GUIDE LEED GREEN BUILDING CERTIFICATION LEED Building Designation & IAQ LIGHT, GUIDE to FORENSIC USE LIGHTING, EXTERIOR GUIDE LIGHTING, INTERIOR GUIDE LOG HOME ENERGY EFFICIENCY LOG HOME GUIDE LOG HOME WALL INSULATION VALUES METHANE GAS SOURCES MOBILE HOME INSPECTIONS MOISTURE CONTROL in BUILDINGS MOLD in FOAM INSULATION, RESISTANCE MOLD INFORMATION CENTER NOISE / SOUND DIAGNOSIS & CURE ODORS & SMELLS DIAGNOSIS & CURE PASCAL CALCULATIONS RADIANT BARRIERS RADIANT HEAT RADIANT HEAT Floor Mistakes to Avoid RADIANT HEAT TEMPERATURES RADIANT SLAB FLOORING CHOICES RADIANT SLAB TUBING & FLUID CHOICES REFLECTIVE INSULATION RIGID FOAM USE INDOORS ROOFING INSPECTION & REPAIR ROOF VENTILATION SPECIFICATIONS SAFETY HAZARDS & INSPECTIONS SEARS KIT HOUSES SHEATHING, FOIL FACED - VENTS SOUND CONTROL in buildings STAIN DIAGNOSIS on BUILDING EXTERIORS STAIN DIAGNOSIS on BUILDING INTERIORS STRESS SKIN INSULATED PANELS STUCCO OVER FOAM INSULATION SUMP PUMPS GUIDE SWEATING (CONDENSATION) on PIPES, TANKS TERMITES TEST KITS for DUST, MOLD, PARTICLE TESTS Thermal Expansion Cracking of Brick THERMAL EXPANSION of HOT WATER THERMAL EXPANSION of MATERIALS THERMAL IMAGING, THERMOGRAPHY THERMAL IMAGING MOLD SCANS THERMAL MASS in BUILDINGS THERMAL TRACKING Indicates Heat Loss THERMOSTATS, HEATING / COOLING VAPOR BARRIERS & CONDENSATION in buildings VENTILATION in BUILDINGS Air Bypass Leaks, Thermal Tracking AIR CHANGE RATE ACH HEAT SAVINGS ATTIC CONDENSATION CAUSE & CURE BALANCED VENTILATION, HEAT COST SAVINGS BATH & KITCHEN DESIGN GUIDE BATHROOM VENTILATION Blocked Soffit Intake Vents BLOWER DOORS & AIR INFILTRATION BLOWER FAN CONTINUOUS OPERATION BLOWER FAN OPERATION & TESTING BRICK or BLOCK WALL CAVITY INSULATION BRICK VENEER WALL AIR LEAKS CATHEDRAL CEILING INSULATION CATHEDRAL CEILING VENTILATION CLOTHES DRYER VENTING COOLING LOAD REDUCTION by ROOF VENTS CRAWL SPACE VENTING & Dryout Procedures HEAT LOSS: How to Calculate Heat Loss in a Building HOT ROOF DESIGNS: Un-Vented Roof Solutions HOUSEWRAP AIR & VAPOR BARRIERS HUMIDITY LEVEL TARGET ICE DAM PREVENTION Inspect Attics for Moisture or Mold Inspect Attics for Blocked Soffit Intake Vents Inspect Basements for Moisture or Mold Inspect Building Exterior - Roof Venting Inspect the Ridge Vent System from the Attic Inspect the Soffit Vent System from the Attic INSECTS & FOAM INSULATION HOUSE DOCTOR, how-to be Insulation Air & Heat Leaks MOISTURE CONTROL in BUILDINGS MOISTURE CALCULATIONS MOISTURE CONTROL in BUILDINGS MOISTURE METER STUDY MOISTURE PROBLEMS: CAUSE & CURE ROOF VENTILATION SPECIFICATIONS ROOF VENTING ENERGY SAVING DETAILS ROOF VENTING NEEDED? SKYLIGHT VENTILATION DETAILS SOFFIT VENTILATION VENTILATION, BALANCED HEAT COST SAVINGS VENTILATION DESIGN PROBLEMS & SOLUTIONS VENTILATION, WHOLE HOUSE STRATEGIES Guide to Sizing House Ventilation Whole House Ventilation Table Installation of Whole House Ventilation VENTILATION, EXHAUST ONLY Single-Port Exhaust Venting Multiport Exhaust Venting Ventilating Heat-Pump Systems VENTILATION, SUPPLY-ONLY Forced-Air Supply Ventilation Multiport Supply Ventilation VENTILATION, BALANCED Heat Recovery Ventilation Energy Recovery Ventilators VINYL CHLORIDE HEALTH INFO VINYL SIDING VINYL Siding or PLASTIC Window ODORS Volatile Organic Compounds VOCs WALL CONSTRUCTION BARRIER vs CAVITY WATER ENTRY in buildings WIND ENERGY SYSTEMS WIND TURBINES & LIGHTNING WINDOWS & DOORS WINTERIZE A BUILDING WOOD, COAL STOVES & FIREPLACES WOOD STOVE SAFETY ZONE DAMPERS ZONE VALVES More Information |
Balanced building air ventilation systems & heating or cooling cost savings: here we explain how to calculate the heating cost savings from using HRVs and ERVs to replace a Ventilation-Only system with balanced fresh air ventilation systems, heat recovery ventilators, and energy recovery ventilators to improve indoor air quality in homes. Green links show where you are. © Copyright 2013 InspectAPedia.com, All Rights Reserved. Author Daniel Friedman. How to Estimate Heat Cost Savings from Installing an Energy Recovery Ventilator (ERV) or Heat Recovery Ventilation (HRV) SystemPage top sketch of HRV or ERV ventilation design is from Best Practices Guide to Residential Construction, by Steven Bliss, courtesy of Wiley & Sons. See VENTILATION, WHOLE HOUSE STRATEGIES for our article series on indoor ventilation for buildings. See ENVIRONMENTAL HAZARDS - INSPECT, TEST, REMEDY for our full list of environmental hazard identification and remedy related to buildings Question: Is there a formula to figure (close guesstimate) the heat loss that can be given a dollar figureI just started managing a 15 story building of about 810,000 Cubic ft of heated space There are 3 exhaust fans on the roof with a total of 6450 CFM of heated air being pulled out of the building 24 hours a day. That's 9,288,000 cubic feet of ventilation a day, That equals 11.46 times the total cubic feet of the whole building a day. My question is, is there a formula to figure (Close guesstimate) the heat loss that can be given a dollar figure. I am trying to convince the heat vac guys to install timers to cut the run time down by half and I would like to put a figure to that amount of savings. This building ventilation system is simply on or off; there is no monitoring system controlling it. The ventilation fans run continuously 24 hrs a day. This system was designed back around 1975 when energy cost was not a big issue. This building is occupied by older people. average age of 75 or so. There are only 27 units in the whole building: 3 penthouses at 6000 sq.ft. and 24 units at 3000 sq. ft. each. There are 2 vacant units at present and usually at least 4 units are empty in winter due to snow birds going where it is warmer in cold weather, and because 3 penthouses serve as second homes and so are rarely occupied). . I don't think that moisture is a problem in this building: it is located in Denver at 5000' and at almost zero humidity! The climate here sucks the moisture right out of your skin and the fans send it into the atmosphere. So we are pumping heated air in the winter and cooled air in the summer right out the door [or in this case, the roof]. I want to suggest that the ventilation fan timers be set to shut off at around 11:00 PM, turning back on at 6:00 AM, off again at 12 noon and back on from 5 PM until 11:00PM. At about 810,000 cubic ft, even at only 12 hours of ventilation run time we are still moving about 6 times the building volume in a 24 hour period. Also I noticed we buy our fuel kind of like a commodity option so If we don't use the agreed upon amount we are penalized which raises the MMBTU by 1.0 - Regards, J.J. Reply: Example Heat Loss and Heat Cost Savings from Using an HRV or ERV
HRV illustration at left is from Best Practices Guide to Residential Construction, by Steven Bliss. That said, here are some things to consider: You Have Described an Exhaust-Only Ventilation SystemThe volume of air that is being removed from the building must be made up by incoming air from outdoors As you have not described any air-to-air heat exchange system, the outgoing heated air is at a net energy cost to the structure. We think you're correct that the effect in heating cost can be calculated. While we cannot offer an exact formula for your building (there are surely other variables), we can give some ideas and a calculation that may help: If you compared the present exhaust-only "total-loss"system with the addition of air-to-air heat exchangers (balanced ventilation) sized to handle the volume of air you are exhausting, the efficiency of the air-to-air system would define how much energy could be regained, measured in BTUs for example. Of course the value varies depending on the difference between indoor and outdoor temperature. You'd work in degree days or average temperature differences. The cost of the air to air heat exchange equipment and its installation to make it work in the building would need to be subtracted from the energy savings to figure the net benefit. Recommended Air Changes per Hour - Formulas & Calculation ExamplesWatch out: the use of the building ventilation system is surely part of an indoor air quality and fresh air requirement. You will want to look at the current building air change rate (ACH) and to compare it to ASHRAE recommendations before you adjust the ventilation fan rate. But as it sounds from your description as if your building uses an "exhaust only" air venting system, indeed it is the most expensive way to improve IAQ. See ASHRAE Standard 62.1 and the ASHRAE handbook for recommended ACH A typical ACH figure would be 5 cubic feet per minute (CFM) per person of occupancy. You could also look directly (by measurement) at the CO2 levels in your building during its time of maximum occupancy as a measure of air freshness. Your building contains by your estimate about 810,000 cubic feet of space. If we assume that's all occupied space, and if we use your figure of 6450 CFM of exhaust-only ventilation, 810,000 cu Ft / (6450cfm) = 125.6 CFM which would be far in excess of the ASHRAE recommendation. Your system is venting 11.46 times the total cubic feet of the whole building a day at 6450 CFM. ASHRAE (Standard 62.1 (CII buildings) and ASHRAE Standard 62.2 (low rise residential buildings) and the ASHRAE Handbook) recommends ventilation rates dependent upon floor area. The minimum ACH was 0.35, but no less than 15 CFM/person. As of 2003, the standards changed to 3 CFM/100 sq. ft. in addition to the 7.5 CFM/person standard.
Here are some looks at the ventilation rate vs. the ASHRAE standard when we plug in your data: A. Using the 3 CFM of venting per 100 sq. ft. guideline:
B. Using the 7.5 CFM of venting per occupant guideline:Let's figure an average of 2 people per unit (empty nesters) in an average of 20 units = average occupancy of 60 people.
It looks as if we have a higher CFM rate than is needed based on the number of occupants. Even using a standard of 20 CFM we'd just be at 1200 CFM total ventilation rate, considerably below 6450. But these two calculations are not the end of the suggested ventilation rate analysis. C. Using the 0.35 Air Changes per Hour Guideline
In sum, it sounds as if the building is being vented more than necessary. Based on calculation "C" above you could reduce your ventilation rate by about 25% and still meet the recommended fresh air standards. We consider calculation "C" as the limiting factor because it exceeds the recommended ventilation standards by less than the other two calculations above. Watch out: These calculations are theoretical only. We are not qualified HVAC engineers. Before changing the building's ventilation system, an inspection and a consult a qualified HVAC engineer would be appropriate. We'd start by reviewing the data to be sure the starting numbers are correct, then repeating these calculations. Also other variables will affect the needed ventilation rates, including building layout and uses, temperatures, pollution concentrations (probably low in your case), etc. Why does Calculation "C" - ACH - Form the Limiting Ventilation Rate Value for This Building?More about Building OccupancyOne more part of the equation. 9 apartments have only 1 person 8 apartments are not full time tenants as I mentioned they are gone form 50% to 90 % and the balance only have 2 people average age being the 70 something but several are in their 90s and 80s They don't cook much and laundry is minimal and bathing is probably minimal as older people are afraid of the shower/tub experience. (Not saying they are dirty just water conservative. Bottom line do yo think we could get to 50% run time and if so considering heat and air what would the approximate savings be? I appreciate the advice of getting an engineer in and doing an analysis of the building. Can We Match ACH and Ventilation to Lower Building Occupancy?Earlier we concluded that "C" or ACH (air changes per hour) appeared to be the measure by which your building was closest to the ASHRAE ventilation recommendations limitation. Here are two more considerations that explain why we don't think that a 50% reduction in ventilation rate (dropping the ACH below 0.35ACH) would be a good idea:
Only if we knew more specifics about how air moves in this specific building (for example with controls that allow ventilation to be increased or decreased within specific apartments or building areas) could we make a reliable plan to drop the ACH rate for unoccupied arts of the structure without fearing that the ACH in the occupied areas would be insufficient. Consider Using Heat Recovery Ventilators to Reduce Heating CostsHowever, pending changes in the numbers for your building, below we suggest an approach to estimating the heating cost savings that may accrue from using an HRV or simply by reducing the exhaust fan rate. You should consider installation of HRVs (Heat Recovery Ventilation) to recover the heat from the exhausted air to return it to the building. HRVs recover only heat and are used primarily in cold climates, while Energy Recovery Ventilators ERVs also recover humidity - which you may not need. ERVs are generally lower in efficiency, that's why we point to HRVs. Quoting from VENTILATION, BALANCED from Best Practices Guide to Residential Construction, by Steven Bliss: Used primarily in cold climates, heat-recovery ventilators (HRVs) pass two air streams by one another within a plastic or aluminum heat exchanger, recapturing 60 to 75% of the heat from the outgoing air stream. This unit, installed in an attic, is hung from chains to reduce noise and vibrations. Recovery of heat from the exhaust air typically ranges from 60 to 75%, if properly installed and balanced. During the summer, if air-conditioning is used, the heat transfer reverses, cooling the incoming hot air. Systems generally have exhaust ports in rooms that generate moisture or pollutants, including bathrooms, laundry, and kitchen and supply ports in bedrooms, living rooms, and other main living spaces. We took a look at your question using advice and calculations in Air-to-Air Heat Exchangers for Healthier Energy-Efficient Homes, by Kenneth Hellevang and Carl Pederson, from North Dakota State University. According to at least one study that published data from the Home Ventilating Institute (link below), in a heating climate an HRV can operate at a sensible heat recovery efficiency of 60 to 66 % (down to 20% in a cooling climate). To calculate an estimate you'd need the floor area, number of square feet, a factor for the division of the interior space into individual rooms (affecting airflow), the building infiltration rate or air changes per hour or number of hours for a complete building air change, the fuel heating cost and the cost of electricity (to operate the heat recovery ventilator) and of course installation costs which for a building like yours might be quite significant. You'll also need the heating degree days figure for your area (HDD). The Heat Cost Savings Formula for Reducing Building Ventilation RateWith that data the heat saved each year (in BTUs) = CFM x HDD X EF x 25.92 where CFM = cubic feet per minute BTU = british thermal unit HDD = heating degree day figure for your area (65 degF - average daily temperature) EF = energy efficiency of the heat exchanger (we use a conservative 50% for a reason explained below) 25.92 = a constant, the specific weight of air Example: using your 9,280,000 cubic feet per day (there are 1440 minutes in a day): 9,280,000 / 1440 = 6,444 CFM [are you sure about that data?] Using a MADE up HDD of 4500 (about half of Fargo ND's figure per year - you didn't say where your building is located) BTU/year saved = 64,444 x 4500 x 0.50 x 25.92 BTU/year saved = 3758 million BTUs for your building - IF our input numbers are really correct. Now if you know your energy cost per heating BTU you can with this formula wildly guesstimate the heating cost effect of a HRV OR of of a 50% reduction in airflow out (turning off the roof fans for half the time or reducing the ACH rate by 50%.) Heat & IAQ Considerations are Different for Commercial and Large buildingsOur energy savings expert Steven Bliss adds these comments: In general, commercial buildings have much larger “internal gains” from people, equipment, lighting, etc., than homes and many need to be air-conditioned year-round for that reason. This would complicate the analysis. The natural rate of air leakage, plus the rate of mechanical ventilation are not strictly additive – more 1 plus 1 = √2. Achieving the recommended level of air exchange may need to take natural air leakage into account. In homes, at least, air-to-air heat exchangers only deliver the rated performance in extremely tight houses. One reason is that balancing the airflows in a leaky house is not possible. The net result is poor performance and too much ventilation. See AIR LEAK DETECTION TOOLS for help with building energy loss due to air leaks. We are not sure how air-to-air heat exchangers work – or if they work at all – at the scale considered in the large building discussed above. The type of equipment, if it exists, is not your little Vermont one-family home basement air-to-air heat exchanger. Ventilation is primarily for people, not for buildings (except perhaps for removal of moisture – usually not a concern in commercial buildings). So we are not sure it makes sense to blast large quantities of air out the roof at night, unless the building is used around the clock. Look Again at the Building Air Change Hourly RateIn sum, from your initial data and the numbers you provided for your building, a careful look at the actual and required air changes per hour data is needed. You may be able to find significant reductions in heat cost by simply making sure that the air exchange rate or ACH is correctly set. Frequently Asked Questions (FAQs)... Ask a Question or Search InspectApediaQuestions & answers or comments about balanced air ventilation systems for buildings and how to design indoor air ventilation systems to cut heating & cooling costs
Ask a Question or Enter Search Terms in the InspectApedia search box just below. Technical Reviewers & ReferencesRelated Topics, found near the top of this page suggest articles closely related to this one.
Books & Articles on Building & Environmental Inspection, Testing, Diagnosis, & Repair
Air Leaks, Moisture Problems, Vapor Barriers & Ventilation in buildings - References, Products
| ||||||